Special EventsNewAccess to the Railway Timetable Tel: 01825 720825You're on the Bluebell Railway web site
Click for Golden Arrow details Vistor Info What's New Shop Search the site FAQ Links Details for the enthusiast How you can join in or help us Contacts Navigate

Carriage & Wagon Works News

LBSCR 6-wheel Fruit/Milk Van No.270 of 1908


31 December 2009

Final assembly, glueing of a bottom-side joint - 2 July 2009 - Jim Hewett Bottom sides being bolted together - 2 July 2009 - Jim Hewett

The last 6 months have seen the base frame for the body assembled on the underframe and this included glueing together the two side bottom rails and completing the sub-floor structure (as seen in the photos above, taken in July 2009). The individual sections are glued together and then bolts added, countersunk into the top surface with nuts and washers underneath.

The next task (later in July, seen in the first photo below) was to loose-fit the floor boards to give a platform to work on to assemble the body frame.

In addition, the "greenhouse" up to this point only had doors on the end large enough to enable the underframe to be shunted in and out. With the impending erection of the body, the end had to be modified to create a larger pair of doors, as seen below.

Loose-fitting floor boards - 16 July 2009 Doors on upper part of the end of the 'shed' - 13 August 2009 - Jim Hewett

body side being fitted - 5 November 2009 - Jim Hewett

 

There was some delay after this as the body framework needed some more attention and several trail assemblies before it could finally be fitted to the base. Once all the pieces of the jigsaw fitted, as seen in the photo on the right mastic was applied to joints (in place of the white lead paste that would originally have been used) and the assembly finally put together for one last time.

Next the roof hoops were fitted, each having to be adjusted individually to give a straight roof line. The four knee brackets which hold the sides to the base were fitted and adjusted to make the sides vertical. Brackets were then fitted between the door and corner posts and the bottom rails.

The photos below, taken on 10th December show most of the hoops aligned. Some however cannot be fixed until after the internal timber cladding has been fitted.


Roof hoops in place - 10 December 2009 Skeleton complete - 10 December 2009 - Jim Hewett

New panels being fitted - 24 December 2009 - Jim Hewett

 

Finally, as seen on the left and below, on Christmas Eve the first of the outer panels were fitted. These are cut from ply, and painted before fitting. We're pleased to find that the 8x4 sheets of ply are a slightly larger metric equivalent, which enables much more economical use of material with less waste, since the panels are just the wrong sizes to come out of sheets that are exactly 8' x 4'.

The other photo is of the new wheel sets and the old one which was used as a pattern. The new ones are Southern Railway disc wheels which have been pressed onto new axles, machined to suit the LBSCR bearings and axle-boxes.

(Report and photos thanks to Jim Hewett)


New panels being fitted - 24 December 2009 Wheelsets - 17 December 2009 - Jim Hewett



June 2009

First assembly of body base frame - 31 July 2008 - Jim Hewett Bottom sides - 14 August 2008 - Jim Hewett

Following the repairs to the underframe detailed in the previous report, the main effort was switched to the body of the van. During the summer of 2008 the base frame for the body was repaired and renewed as necessary. All the outside rails were renewed, the side rails each having to be fabricated from four pieces of timber which will be glued and bolted together when fitted to the underframe. There was a trial assembly of the base frame towards the end of summer 2008 (photo above left). The second photo above shows how the bottom side rails are bolted together.

Work then commenced on the repair of all the body frame sections and that continued until mid 2009. In the meantime the new bottom rails had been prepared to accept the body frame sections. By May 2009 enough work had been done to trial assemble the whole body framework on the workshop floor (photo below) but this produced a further list of jobs to be done before the body was ready for assembly on the underframe. This occupied the team up to the end of June.

Interestingly, during restoration it was noticed that there were numbers stamped into the door pillars (second photo below) which probably refer to folding shelves as there is evidence of hinges being fitted close by. It is hoped to restore this feature.

Trial assembly of body framework - 21 May 2009 - Jim Hewett Shelf numbering and hinge position on door pillar - 28 May 2008 - Jim Hewett

Underframe lifted to remove centre wheelset - 24 June 2008 - Jim Hewett

 

New wheels and axles are required and on 24 June 2009 the underframe was lifted using the new electric jacks to remove the centre wheelset which was sent away as a pattern for the axles. This was the first use of the jacks, but their use on heavier loads must await construction of the proper jacking pads alongside the track between the pit and 270's plastic home.

Some work has been done to restore the vacuum brakes and parts have been acquired to add air brakes also.

(Report and photos thanks to Jim Hewett)



Spring 2008

270 re-wheeled - 27 March 2008 - Jim Hewett
Hopefully updates on this project will now become more frequent. Jim Hewett has provided the photo above, which shows the underframe now repaired and re-wheeled. To fill in the story since the last report, illustrated in the photos below, the van body has been dismantled, with careful notes being made of all positions of internal fittings and shadows left by ones removed. Whilst this design was designated as a Milk/Fruit van, the positions and size of shelves indicates that this one was probably dedicated to fruit traffic.

The underframe was then stripped down, and repairs made to the ends of the timber solebars, and both headstocks replaced. The most expensive part so far has been replacement of the steel flitch-plates along the outside of the underframe, requiring many holes drilled in precise places. The inner flitch plates, shorter sections, were in better condition and have been repaired as necessary and refitted.

Since the photo above was taken in March, the progress has been on two fronts; one team is refitting and adapting the brakes for a dual vacuum/air system whilst another team is preparing timber for the base of the body.

270 being dismantled - 15 March 2007 - Jim Hewett 270's underframe after removing the body - 5 July 2007 - Jim Hewett

Above left: The van in the course of being dismantled (March 2007)
Above right: The underframe after removal of the body, about to be lifted from its wheels (July 2007) (Photos: Jim Hewett)

270's underframe - 20 May 2007 - Dave Clarke 270's underframe with wheels removed - 8 July 2007 - Dave Clarke

Above left: The van's underframe - this photo shows the generally good condition of the underframe timbers (May 2007)
Above right: The solebars stripped of all brake gear, with the wheels removed (July 2007)
Below left: The new ends grafted onto the solebars (Nov 2007)
Below right: The new steel flitch plates drilled and ready for cleaning, painting and fitting (Jan 2008) (Photos: Dave Clarke)

Ends grafted onto the solebars - 4 November 2007 - Dave Clarke The new flitch plates drilled - 6 Jan 2008 - Dave Clarke


January 2007

270's temporary shed - 3 Feb 2007 270 buffers removed - 3 Feb 2007
Most of the covering is now on the temporary building, such that the main dismantling can now proceed. One task undertaken before the covering was installed was the unthreading of the 14-ft length of the buffers and the drawgear, as can be seen lying alongside the carriage in the second photo above.

The photos below show that the doors and external panelling have been removed, and that much of the internal planking has also been numbered up, and some of that removed.

Side of 270 - 3 Feb 2007 Interior of 270 - 3 Feb 2007

270 Dave Clarke Aug 06

Work started 29 October 2006

The photo on the right by Dave Clarke, shows the building part-way through erection, in August 2006, with Van No.270 beneath its tarpaulin.

Over the last few months the framework of the temporary building which is to house the van during its overhaul has been completed. It still awaits its external covering, but work has started on the van itself, which is still under its tarpaulin.

The Thursday Gang have removed the external doors and cleared the interior. As much evidence about the van's history as possible is being gathered whilst dismantling of the interior starts.

Funding for the project is provided thanks to a bequest left to the Bluebell Railway Trust for that specific purpose.

splash


Return to the web page for this van, or the Carriage & Wagon Works News or main Carriage and Wagon page
Go to Bluebell Home Page, to the Timetable or to Special Events
Visitor Info. - Catering - Contacts - What's New - Extension - Locos - Carriages & Wagons - Signals - History - Other - Links - Search the site - FAQ
Why not become a BRPS Member?     -     Get more involved as a Volunteer

Your ideal Film/TV location?


Valid HTML 4.0 Transitional! Last updated 2 January 2010 by Richard Salmon
© Copyright, credits and disclaimer.