
Click for latest re-signalling progress.
![]()
After a long gestation period plans were finally agreed for renewal of the track layout at Horsted Keynes, obviously impinging on the Signalbox.
Left: Horsted Keynes Signalbox in the days before the work began. Photograph: Richard SalmonThe old arrangement had the former number three road up starter and the point leading to numbers two and three roads controlled by a ground frame which in turn was under the overall control of the signalman in the box. This point did not have a lock for movements into the former number three road, resulting in all down passenger trains having to use the then number two road. Although the old numbers one and two roads do join north of the station, at "Leamland Junction", this had not been an operational route and trains could only enter or leave number one road from the south. We now have bi-directional running on all roads, so the new changes included making "Leamland Junction" operational and installing locking for movements south into what was number three road. When all of this trackwork was completed the points involved were then worked directly from the box.
Better signalling of the approach from the north (and at the same time a move further up the line for the advanced starter) created a demand for additional capacity on the signal box's frame. When considering as well the plans for the change to the layout south of the station, forty levers on their own appeared to be insufficient for our needs. Several ideas were put forward to cope with this problem, only two of which were really practical. The first was to build a replica, but bigger, box to replace the existing one (whose structure was in sore need of repair), and the second to enlarge the existing box whilst at the same time repairing it.
Neither of these options was, however, available as early in 1997 someone applied for, and obtained, a grade two listing for the whole Horsted Keynes station area, especially mentioning the signal box. We could knock it down in the interests of safety, but we could not modify its fabric in the slightest way!
So, where to go next? It was decided to have some functions operating remotely, as for the down distant signal at Sheffield Park. This means quite a few power-worked points and signals, a move which was not very popular but is, however, the best course of action and the one that is being instigated.
Work Progress
By clicking on the images you will be taken to a larger version, which may have more content than the smaller version on this page.
First Quarter 2013
This site has been rather quiet for the past year due to the emphasis of S&T work being on the push to East Grinstead, though attention has now turned back to Horsted Keynes.
Further signalling functions at Horsted Keynes have been converted from electrical to mechanical operation. The photo of the switches illustrates what is left to be transferred to the lever frame and the screw holes in the wall are a measure of progress so far.
A side effect of this piecemeal conversion is the interesting ergonomic impact of setting routes, with a combination of switches and levers. For example the photo of the lever frame has the route cleared for the Up Golden Arrow through Platform 2. This involves alternating from switch to lever several times i.e. 40 Outer Home (switch); 22 points & 37 Inner Home (levers); 31 Platform Starter (switch); 5 points and 29 1st Advance (lever); 28 2nd Advance (switch). The Signalling diagram should help to explain the sequence.
The remaining switches.
The frame with many of the levers now in use.
The Signalling diagram.
Text and photographs: Chris Majer
Last Quarter 2011
Work is progressing with the transfer of signals back to the lever frame. The stumps, pulleys and wheels are in place from the box right up to the Up Second Advance Starter, a distance of about half a mile. Two shunt signals at the north end of the station have just been added to the frame (13 and 18) allowing two of the position light shunt signals to be removed. Approximately half of the levers are now in use with much of the preparation work track-side ready for the next batch of conversions. The most tricky part of the process is the stage-works required in the relay room to ensure the transfer of locking from electrical to electro-mechanical is carried out safely.
The stumps in place northwards with the wires for 13 and 18 shunts.
The lead-away at the signal box with the wires ready for extending to the individual signals.
Nº13 lever just after its function was transferred to the frame.
Text and photographs: Chris Majer
Second Quarter 2011
All points are now operated from the lever frame and the signals are being transferred. So far numbers 39 (Up Calling-on) and 37 (Up Inner Home) have been transferred. The signal wire stumps and trackside pulleys and selectors are being installed and the Down Yard Shunting Gong has been reinstated, operated from a separate lever positioned by the South end windows. Some of the electrically operated semaphore signals are being converted to mechanical operation to restore the traditional method of operation and to release signal machines for the Kingscote resignalling project.
Levers in the Horsted frame. The black and blue one 'out' of the frame is for points 17 and the lock and the red one for Signal 37.
Newly installed Signal Wires leading away from the 'box.
The lever for the Shunting Gong at the south end of the 'box now reconnected to the Gong.
Text and photographs: Chris Majer
First Quarter 2010
The main change at Horsted Keynes is the ongoing transfer of point operating functions from the switch panel to the lever frame. By the end of March points 20, 22, 23 and 25 had been transferred. There have also been changes to some interlocking controls to tighten up the requirements for the signalling system. These include approach release of the Up Outer Home, where reduced overlaps apply beyond the Up Inner Home, and changes to the Down Inner Home when signalled into Platform 2 with an overlap set beyond the Down Platform Starter towards the Ardingly Branch.
The main S&T activity is presently not for Horsted but is concentrating on resignalling the north end of Kingscote Station with a new control panel installed in the presently operational temporary Kingscote Signal Box, awaiting the installation of track circuits, point machines and signal operating equipment. This work is required for the operation of the Kingscote - East Grinstead section.
The other main activity is the preparation of equipment ready for installation at East Grinstead. Two Ground Frames are required to work the run-round facilities and the access to the Network Rail infrastructure.
Levers in the Horsted frame. The two black and blue ones 'out' of the frame are for points 20 and 25 and their locks.
The panel instruments being installed at Kingscote for the extension to East Grinstead.
The two Ground Frames at Horsted that will be installed for working the East Grinstead run-round loop and access to Network Rail.
Text and photographs: Chris Majer
Third Quarter 2009
All of the locks and controllers are in place and are progressively being wired up to the distribution wiring frame on the wall of the locking room. When the links are inserted the wiring will be through connected to the relay room on the other side of the Up Yard Ardingly Siding.
The photograph of the locks and controllers with the covers removed, reveals the electric lever locks in the vertical plane and the controllers in the horizontal plane. The locks are in addition to the mechanical locking and provide, for example, back locks for the levers as well as point locking when the track circuit shows occupied.
The commissioning of the lever frame will take place in phases with first phase being the transfer of all points from the switches to levers in one session. This will leave a period where the signalman will operate the points on the lever frame but the signals by use of the temporary switches.
The distribution wiring frame.
Electric lever locks in the vertical plane and controllers in the horizontal plane.
Overview.
Text and photographs: Chris Majer
Second Quarter 2009
The Locks and Controllers have now been installed although not mechanically connected yet to allow the Signalmen to operate the levers with just mechanical locking so that they can operate the frame and get familiar with the new arrangement.
The pullies for the signal wires have been installed and despite the apparent random arranagement, have been carefully positioned so that the wires do not interfere with each other and can be routed via the adjusters for the long runs to the furthest signals.
The latest items installed in the locking room. Text and photographs: Chris Majer
The mechanical locking is now complete and a walkway has been constructed over the operating floor locking trays. The work has now shifted to downstairs in the locking room where the electrical locking is being applied.
Bert Bassett, one of the Bluebell's original Signalmen, inspecting the completed frame.
The walkway that has been constructed over the locking trays.
Charles Hudson, S&T leader, in the locking room downstairs where work has started on the electrical locking.
Text and photographs: Chris Majer
First Quarter 2009
The new mechanical locking for Horsted Keynes lever frame has been completed and provisionally tested. The mechanical actuators for the Sykes treadles and the train waiting indicator have been connected up. Work is currently progressing with fitment of pulley wheels for the wire operated signals. Many of the mechanical signals currently electrically operated using signal machines, will revert to mechanical operation and the recovered equipment transferred to Kingscote in readiness for the East Grinstead extension commissioning.
The lever frame inside the 'box with the mechanical locking completed.
The lever frame and block shelf looking almost ready for use!
The mechanical actuators for the Sykes treadles and the train waiting indicator connected up under the Block Shelf.
Text and photographs: Chris Majer
First Half 2008
Most of the components to reassemble the locking are now ready and the next stage will be to refit the interconnecting bars and dogs in the locking trays upstairs (there are more downstairs) and attach the tappets to the levers (see photo of the lever frame). The interconnecting bars and lock dogs are ready and waiting downstairs under the signal box. Some components will need to be customised as the assembly work progresses because of tolerances with a large mechanism such as this. The picture on the right shows two interconnecting locking bars that are so long that they almost go from one end of the frame to the other!
The tappets sitting by the frame.
The locking pieces presently underneath the 'box.
The long interconnecting bars. (Click to see the full image).
Text and photographs: Chris Majer
All photographs are © copyright. Non-accredited pictures are © Peter RichardsThe page showing the changes to the track layout at Horsted Keynes over the years may be of interest.
Updates from 1997 to 2000 are in the HK Signalling Work Archive 1,
for 2001 to 2003 in the HK Signalling Work Archive 2
for 2004/2005 in the HK Signalling Work Archive 3,
and for 2006/2007 in the HK Signalling Work Archive 4![]()
Return to Bluebell Home Page, to the Timetable or to Special Events
Signalling - Signal Boxes - The Signals - Bell Codes - Horsted Keynes Re-signalling
Signal Box Diagrams for Kingscote - Horsted Keynes - Sheffield Park
Visitor Info. - Catering - Contacts - What's New - Extension - Locos - Carriages - Signals - History - Other - Links - Search & Index - FAQ
Why not become a BRPS Member?Get more involved as a Volunteer
This page last updated 10th March 2013 by Peter Richards.
Text Copyright © and named contributors. Credits and disclaimer.