Current Infrastucture News
Archive of Infrastucture News: 2013-14 - 2015-16 - 2017 - 2018 - 2019 - 2020 - 2021-22 - 2023
Archive Reports: Northern Extension Project -
Permanent Way and Lineside News (2007-2011) - P-Way News (2002-4)
The Bluebell Railway's Extension:
Progress towards East Grinstead
Archive 3 (2002)
Extension Project archives:
2012 through to re-opening -
2011 -
2010 -
2009 -
2008 -
2006-7 -
2004-5 -
2003 -
2002 -
April - Dec 2001 -
Oct 2000 - Feb 2001 - April 2000
Latest News page
17 December 2002 - Winter Weather!
Now that the weather has deteriorated we have had to suspend the use of
mechanical plant to avoid damaging the trackbed and on safety grounds.
Unless there is a significant period of dry weather we will be unable to
restart this work until the spring.
The opportunity is now being taken to tidy up the banks and embankments.
Using a combination of strimmers and hand tools, vegetation that has grown up
during the past two years is being cut back and burnt. This kind of work is
particularly suitable for anyone who is steady on their feet and doesn't
mind working in the (sometimes very) fresh air.
Work commenced near the
cattle creep near Hazelden Farm and will continue north towards Imberhorne
tip. If we complete that before the weather improves then a start will be
made working south from Hazelden. The picture was taken looking north
towards the tip before work started.
Just a short note regarding the previous news "First pass clearing
Foster's Tip". This has been interpreted by some of the national
railway press as indicating that we are half way through clearing
Imberhorne tip. Unfortunately these are two entirely separate tips, and
Imberhorne tip will be a much bigger undertaking!
14 October 2002 - First pass clearing Foster's Tip
We have completed the first "pass" removing the waste dumped in the cutting
by Ash Lea Farm. Progress has been restricted by the availability of plant
to cart the excavated material away.
We have now commenced a second "pass" to remove further material and we
have located the base of the original bank in this area.
There is still a considerable volume of material to remove. For many weeks
the weather on Saturdays has been favourable for our work, however, we will
not be able to continue once the real winter rains set in.
The photograph shows that we are beginning to see something approaching the
original width of trackbed.
Work is also now being undertaken by contractors on the refurbishment of
Hill Place viaduct on the outskirts of East Grinstead. This photo by Jon
Bowers shows progress in clearing the vegetation which was damaging the brickwork, and repairs to the parapet, including the relacement of original blue
capping bricks. It must be emphasised
that there is absolutely no access to the Viaduct as it is a working
site.
28 August 2002 - Clearance at Ash Lea Farm
North of the dam (which is no more) debris that had been scraped from the
formation and piled to the side has been removed. This work is not yet
complete but the bulk of the sludge that had been in the water behind the
dam has now been removed.
In recent weeks we have commenced excavating the waste that had been dumped
on the trackbed on the land that was purchased from Ash Lea Farm. This will
take some time as it comprises a mixture of soil, scrap metal and general
farm waste. Hopefully the weather will continue to remain favourable as
heavy rain will cause the formation to become soft and deteriorate under the
weight of the JCB and dumpers. When it becomes too wet we shall stop this
type of work until it is suitable to use the plant again.
The picture on the left was taken on Saturday 24th August and is looking north
between Ash Lea Farm and Mr. Steer's land. The current work can be seen on
the left. Once the first "pass" is complete a second pass will be made to
reinstate the alignment of the original cutting. The current rate of
progress is about ten meters per day so there is still a considerable amount
to do.
19 August 2002 - Work starts on the Viaduct
Clearing the scrub and vegetation around the bases of the arches
under Imberhorne viaduct has been undertaken in preparation for the
start of major restoration work, which commenced on 19th
August. We have worked closely with the local authorities with this
work and Chris White, the extension gang and Friends of Kingscote
members have mail dropped our neighbours to tell them of the
impending work and giving them a "hotline" number to contact if there
are queries or problems.
The good news is that the large majority of callers were very
supportive of Bluebell and welcomed its arrival. Several neighbours
asked if we could leave a screen of trees which we have accommodated
but have left a "corridor" by the base of the viaduct and ensured the
clearance is as environmentally friendly as possible. Fencing has
been re-instated in accordance with the requirements of the HSE.
We would like to remind everyone that the viaduct is now a
construction site and access will not be permissible under any
circumstances unless approved and under escort.
15 May 2002 - Further drainage and clearance
Lack of news does not mean that nothing has been happening during the last
few months. We have been tidying the trackbed and banks that have already
been cleared. We have also installed a drain across the width of the
trackbed south of Mr Steer's land to link with the drainage ditch that flows
along the boundary of Ash Lea Farm. This has enabled the land purchased from
Mr Steer to be scraped down to the original trackbed and the water here now
drains along the east side. On 11th May work finally started on the removal
of the dam across the width of the trackbed at Keepers. This will take some
time but will allow the drainage north of the dam to be improved.
The photographs taken last Saturday (courtesy of Nigel Longdon) show the
removal of the dam which formerly retained a large pond on the trackbed at
Keepers.
Return to BRPS Home Page,
to the Timetable or to Special
Events
Current Infrastucture News
Archive of Infrastucture News: 2013-14 - 2015-16 - 2017 - 2018 - 2019 - 2020 - 2021-22 - 2023
Archive Reports: Northern Extension Project -
Permanent Way and Lineside News (2007-2011) - P-Way News (2002-4)
Extension Project archives:
2012 through to re-opening -
2011 -
2010 -
2009 -
2008 -
2006-7 -
2004-5 -
2003 -
2002 -
April - Dec 2001 -
Oct 2000 - Feb 2001 - April 2000
Visitor Info. -
Museum -
Trust -
Catering -
Contacts -
What's New -
Projects -
Locos -
Carriages & Wagons -
Signals -
History -
Other -
Links -
Search -
FAQ
Why not become a BRPS Member? -
Get more involved as a Volunteer
Your ideal Film/TV location?
Page edited by Richard Salmon.
Thanks are due to Jim Turtle, Nigel Longdon, Roy Watts and Geoff Harris.
© Copyright BRPS. Privacy Policy
|